# Manual answer key
Synthetic project and people; no captured AI result or actual access test.
- S3 supersedes full rollout 10 October. Pilot 12 October conditional on retest and approval; not approved to launch.
- S2 green headline is stale relative to S3's open defect.
- S1 retirement 31 October remains documented and unresolved against revised rollout; cannot silently cancel or declare safe.
- Export retest unowned. Leah proposed, not accepted. Ava departure 9 October makes transfer timely but does not create ownership.
- Existing rollback instructions do not prove successful rehearsal.
- Document access confirmed only within synthetic fixture; production access pending.
- Action closure requires evidence, owners' acceptance and required approval. Draft completeness is not handover acceptance.